  • That depends on your team composition. Decoupling story points and hours means that the points indicate the complexity of the task; each developer might take a different amount of time to deliver that depending on their ability and expertise in that part of the system. The points give you a simple metric to show how much complexity the team have left to deliver, and tasks get assigned to whoever is best placed to deliver them at the time.